Question: Consider the feedback system shown in Figure P9.28 with the process transfer function given as The controller is the proportional controller Gc(s) = KP (a)
-1.png)
The controller is the proportional controller
Gc(s) = KP
(a) Determine a value of KP such that the phase margin is approximately P.M 45°.
(b) Using the P.M. obtained, predict the percent overshoot of the closed-loop system to a unit step input.
(c) Plot the step response and compare the actual percent overshoot with the predicted percent overshoot.
FIGURE P9.28
A unity feedback system with a proportional controller in the loop.
-2.png)
G(s) = . s(s + 1) Controller Process + - Eds) Kp Y(s)
Step by Step Solution
3.38 Rating (167 Votes )
There are 3 Steps involved in it
The loop transfer function is When KP 1414 we have PM 45 Using the approximation that ... View full answer