Question: Using the network above and the additional information below, find: (a) The crash cost per day (b) Which activities should be crashed to meet a
Using the network above and the additional information below, find:
(a) The crash cost per day
(b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost. Assume partial crashing isallowed.
.png)
Crash Crashed Normal Time Cos Tim Normal Activity (days) (total) (days) Cost $300 250 400 150 $500 325 550 250 4
Step by Step Solution
3.44 Rating (179 Votes )
There are 3 Steps involved in it
a Activity Crash Days Crash Crash Day A 1 20000 20000 B 2 7... View full answer