Question: Consider the following set of activities: a. Draw the CPM network for this problem. (Remember that a CPM network requires unique start and finish nodes.)
Consider the following set of activities:
.png)
a. Draw the CPM network for this problem. (Remember that a CPM network requires unique start and finish nodes.)
b. Manually determine the earliest and latest start and finish times for each activity and the amount of slack for each activity.
c. What is the critical path?
d. How long should it take to complete the project?
e. Verify your answer to part c using MicrosoftProject.
Activity Required Days 9 Predecessor Activities A, B A, B
Step by Step Solution
3.24 Rating (176 Votes )
There are 3 Steps involved in it
a b Activity Predecessor Time EST EFT LST ... View full answer