Question: Consider the supply chain planning implementation project depicted in Figure 16S-1. Suppose that the client has offered a $4,000 bonus to us if we can
Consider the supply chain planning implementation project depicted in Figure 16S-1. Suppose that the client has offered a $4,000 bonus to us if we can complete the project seven working days early. Based upon the crash cost information provided in Table 16S-1, would you accept the client's proposal? By how many days could you profitably shorten the project?
Step by Step Solution
3.40 Rating (181 Votes )
There are 3 Steps involved in it
Activity to Crash Crash Cost Critical Path Length Notes 0 31 days No tasks crashed 1 Set Sy... View full answer