Question: Using the diagram you created in question 5, calculate ES,EF, LS, LF for each task and the amount of slack. List the tasks that appear
In questions 5
Task A, duration 2, no dependency
Task B, duration 4, no dependency
Task C, duration 7, no dependency
Task D, duration 5, depends on Task A
Task E, duration 3, depends on Task B and Task C
Task F, duration 8, depends on Task C
Task G, duration 10, depends on Task D and Task E
Task H, duration 4, depends on Task E
Task I, duration 7, depends on Task F
Task J, duration 12, depends on Task H and Task I
Step by Step Solution
3.50 Rating (167 Votes )
There are 3 Steps involved in it
A ES0 EF2 LS17 LF19 B ES0 EF4 LS11 LF15 C ES0 E... View full answer