Question: Dorben Co. provides a 10% allowance for its operators. A work sampling study of one operator over an 8-hr shift yields the following data. Average
a. What is the observed time (in minutes) for loading?
b. What is the normal time for unloading?
c. What is the overall standard time ?
d. What is the accuracy of the study?
.png)
Load Unload Process Idle
Step by Step Solution
3.33 Rating (171 Votes )
There are 3 Steps involved in it
a 1650 480 min50 units 307 minunit b 1... View full answer