Question: Dorben Co. provides a 10% allowance for its operators. A work sampling study of one operator over an 8-hr shift yields the following data. Average

Dorben Co. provides a 10% allowance for its operators. A work sampling study of one operator over an 8-hr shift yields the following data. Average rated performance is 110%.
a. What is the observed time (in minutes) for loading?
b. What is the normal time for unloading?
c. What is the overall standard time ?
d. What is the accuracy of the study?
Load Unload Process Idle

Load Unload Process Idle

Step by Step Solution

3.33 Rating (171 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a 1650 480 min50 units 307 minunit b 1... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1439-B-H-R-M-E-R(669).docx

120 KBs Word File

Students Have Also Explored These Related Human Resource Management Questions!