Question: Reconfigure the Gantt chart in problem 2 to include some different predecessor relationships. Optional: Solve this problem with Microsoft Project. a. Assume that activities B
Reconfigure the Gantt chart in problem 2 to include some different predecessor relationships. Optional: Solve this problem with Microsoft Project.
a. Assume that activities B and C are linked with a “finish to finish” relationship. Does that change the expected completion date for the project?
b. For activity F, add a lag of three days to its predecessor relationship with activity D. By adding the 3-day lag to F, what is the new expected duration for the project?
c. Suppose you now added a start to start relationship between activities F and G to the new Gantt chart. How does this additional relationship change the expected completion date for the project?
Step by Step Solution
There are 3 Steps involved in it
a No linking Band C in a finish to finish relationship will not a... View full answer
Get step-by-step solutions from verified subject matter experts
