Question: Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June.
Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June. Complete the earned value column on the right. Assume the project is planned for a 12-month duration and $250,000 budget.
.png)
Step by Step Solution
There are 3 Steps involved in it
Activity Jan Feb Mar Apr May Jun Plan C Value Staffing 8 7 15 100 15 Blueprintin... View full answer