Question: A small sample of your projects PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for

A small sample of your project’s PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for a confidence level for this activity. You tell them there is a 95.44 percent chance of completing activity 2 within how many days?Activity 1 23 Optimistic Pessimistic Likely Expected Value 10 14 12 20

A. Between 18 and 28 days B. Between 21 and 25 days C. Between 13 and 33 days D. Between 23 and 28 days

Activity 1 23 Optimistic Pessimistic Likely Expected Value 10 14 12 20 30 23 3 3 3