Question: Five tasks are scheduled to be completed in sequence. Each task has a finish-start relationship with the next task. Each has one day of total

Five tasks are scheduled to be completed in sequence. Each task has a finish-start relationship with the next task. Each has one day of total float. As of today, task one and two have been completed on schedule.

How many days of float remain in the schedule for these tasks?

a. Two

b. One

c. Zero

d. Four