Question: From the following network data, determine the critical path, starting and finishing times, and TFs and FFs. Activity Description ST A B D E F
From the following network data, determine the critical path, starting and finishing times, and TFs and FFs.

Activity Description ST A B D E F G H I J END Start milestone Excavate stage 1 Order, deliver steelwork Formwork stage 1 Excavate stage 2 Concrete stage 1 Formwork stage 2 Backfill stage 1 Concrete stage 2 Erect steelwork Backfill stage 2 End milestone Duration 4 7 4 5 WN Un 8 2 3 8 10 5 - Immediate Predecessors ST ST
Step by Step Solution
3.42 Rating (155 Votes )
There are 3 Steps involved in it
Sure I can help you determine the critical path starting and finishing times and TFs and FFs for the network data in the image Critical Path The critical path is the longest path through the network a... View full answer