Question: Using the earned value analysis technique, a project manager calculates a schedule performance index of 0 . 7 5 and a cost performance index of

Using the earned value analysis technique, a project manager calculates a schedule performance index of 0.75 and a cost performance index of 1.25. To bring the schedule back on track, the project manager decides to allocate additional resources to critical activities to complete them faster. Which technique are they using to control the schedule?
Question 13 options:
leads and lags
crashing
fast tracking
resource optimization