Question: Using the earned value analysis technique, a project manager calculates a schedule performance index of 0 . 7 5 and a cost performance index of
Using the earned value analysis technique, a project manager calculates a schedule performance index of and a cost performance index of To bring the schedule back on track, the project manager decides to allocate additional resources to critical activities to complete them faster. Which technique are they using to control the schedule?
Question options:
leads and lags
crashing
fast tracking
resource optimization