Question: During the Control Scope process, analysis of the scope performance resulted in a change request to the scope baseline. This change request will be processed
During the Control Scope process, analysis of the scope performance resulted in a change request to the scope baseline. This change request will be processed for review and disposition in the:
Control Quality Perform Integrated Change Control Monitor and Control Project Work Validate Scope