Question: On March 1, 2012, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The
On March 1, 2012, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2014. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2012, 2013, and 2014 are given below.

Instructions
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2012, 2013, and 2014 (Ignore income taxes.)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2012, 2013, and 2014 (Ignore incomes taxes.)
Step by Step Solution
3.45 Rating (165 Votes )
There are 3 Steps involved in it
a ProfitLoss to be recognized using percentageofcompletion method 2012Total contract costs incurred ... View full answer
Get step-by-step solutions from verified subject matter experts
