Question: Using the job information in Problem 24, develop a sequence based on the shortest processing time priority rule. Prioritize based on prep time. In the
Using the job information in Problem 24, develop a sequence based on the shortest processing time priority rule. Prioritize based on prep time. In the case of ties, select the house that has the smallest paint time.
(a) Calculate the makespan.
(b) Calculate the mean job flow time associated with this sequence.
(c) Calculate the average number of jobs in the system with this sequence.