Question: Using the job information in Problem 24, develop a sequence based on the shortest processing time priority rule. Prioritize based on prep time. In the
(a) Calculate the makespan.
(b) Calculate the mean job flow time associated with this sequence.
(c) Calculate the average number of jobs in the system with this sequence.
Step by Step Solution
3.40 Rating (162 Votes )
There are 3 Steps involved in it
a Makespan 29 days b Mean job flow time ... View full answer