Consider the project information in the table below: Draw and analyze a project network diagram to answer

Question:

Consider the project information in the table below:image text in transcribed

Draw and analyze a project network diagram to answer the following questions:

a. If you were to start on this project, which are the activities that you could start on at the very beginning of the project?

b. How many paths are there in this project network?

c. What is the critical path through this network? What is the completion time of this project?

d. What is the earliest that activity G can possibly be completed?

e. What is the most that activity F can be delayed in starting, without delaying the project?