Question: Consider the project information in the table below: Draw and analyze a project network diagram to answer the following questions: What is the most that

Consider the project information in the table below: Draw and analyze a project network diagram to answer the following questions: What is the most that Activity E can be delayed in starting, without delaying the project? A. 22 B. 21 C. 20 D. 19 E. 18