Question: Task C has two immediate followers, tasks D and E. Task D has a late start time of 10 days and task E has a
Task C has two immediate followers, tasks D and E. Task D has a late start time of 10 days and task E has a late start time of 8 days. What is the late finish time of task C?
Step by Step Solution
3.38 Rating (148 Votes )
There are 3 Steps involved in it
The late finish time for task C which has two immediate follo... View full answer