Question: The WBS, estimates for each work package, and the network diagram are completed. Which of the following would be the NEXT thing for the project
The WBS, estimates for each work package, and the network diagram are completed. Which of the following would be the NEXT thing for the project manager to do? A. Sequence the activities. B. Verify that they have the correct scope. C. Create a preliminary schedule and get the team's approval. D. Complete risk management.