Question: The fast-tracking method of schedule compression involves: A. The use of industrial engineering techniques to improve productivity, thereby finishing the project earlier than originally planned.
The "fast-tracking" method of schedule compression involves: A. The use of industrial engineering techniques to improve productivity, thereby finishing the project earlier than originally planned. B. Performing activities in parallel, thereby increasing risk. C. Going on a "mandatory overtime schedule" in order to complete the project earlier. D. Assigning "dedicated teams" to the critical path activities.