Question: The fast tracking method of schedule compression: Question 1 8 options: A ) Assigning dedicated teams to critical path activities to achieve project schedule objectives.
The "fast tracking" method of schedule compression:
Question options:
A
Assigning "dedicated teams" to critical path activities to achieve project schedule objectives.
B
Performing in parallel for at least a portion of their duration activities or phases that normally done in sequence, which may result in rework and increased risk.
C
Going on a "mandatory overtime schedule" to complete the project on schedule or earlier if possible.
D
The use of industrial engineering techniques to improve productivity, thereby finishing the project earlier than originally planned.