Question: The fast-tracking method of schedule compression involves: The use of industrial engineering techniques to improve productivity. A) Overlapping work phases to be executed, thereby increasing
The fast-tracking method of schedule compression involves:
The use of industrial engineering techniques to improve productivity.
A) Overlapping work phases to be executed, thereby increasing risk.
B) Going on mandatory overtime schedule in order to complete the project earlier.
C) Calculating the percentage of potential schedule overrun and reducing each activitys duration by that percentage in order to enable the project to complete on schedule.
D) Assigning dedicated teams to the critical path activities