Question: You're managing the project cited in question 34 using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The
You're managing the project cited in question 34 using the earned value technique (EVT) for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual value (AV) is $150,000. What is the schedule performance index (SPI) for the project? A. 0.5 B. 1.5 C. 1.75 D. 2