Question: Assume that the maximum resource hours available per week are 10. Which weeks are overcommitted? consider a project with the following information: Activity Duration Predecessors
Assume that the maximum resource hours available per week are 10. Which weeks are overcommitted?
consider a project with the following information:


Activity Duration Predecessors EFG I 3 5135 ABC D | A A B, C B 4 D 2 C H 5 E, F, G