Question: 7. Cost and schedule data for a small project are given below. Assume an indirect cost of $200/day. Develop the time-cost curve for the project

7. Cost and schedule data for a small project are given below. Assume an indirect cost of $200/day. Develop the time-cost curve for the project and determine the minimum contract duration.

Cost ($) Duration (days)

Activity Preceded by Crash Normal Crash Normal A 3900 3600 6 7 8 A 6500 5500 3 5 C 8 7200 6350 7 9 0 8 4900 4700 18 19 E B 2200 2050 9 10 F C 1700 1200 6 8 G F 7200 7200 5 5 H E 10000 9450 10 11 I 0, G, H 4700 4500 6 7