Question: A system development project is nearing project closing when a previously unidentified risk is discovered. This could potentially affect the project's overall ability to deliver.

A system development project is nearing project closing when a previously unidentified risk is discovered. This could potentially affect the project's overall ability to deliver. What should be done next? A. Alert the project sponsor of potential impacts to cost, scope, or schedule. B. Qualify the risk. C. Mitigate this risk by developing a risk response plan. D. Develop a workaround.