Question: During the development of a software development project's project management plan, the project management team decides to build a working environment where a self-organizing team
During the development of a software development project's project management plan, the project management team decides to build a working environment where a self-organizing team can do their work without any centralized control.
What needs to be specially taken into consideration while doing resource planning?
A. Acquire an industry-standard subject matter expert from the market.
B. Appoint a technical architect to play the role of a project manager. C.
Ensure that the project scope is defined in detail.
D. Acquire generalized specialists.