Question: One project activity must start with a one-week delay from the start of another. What method should be used to represent that dependency in a

One project activity must start with a one-week delay from the start of another. What method should be used to represent that dependency in a network diagram?

A. Critical path method B. Activity on arrow C. Activity on line D. Activity on node