Question: The Inputs to the Control Procurements Process include the following: A) The Requirements Management Plan, the Risk Management Plan, the Procurement Management Plan, the Change
The Inputs to the “Control Procurements” Process include the following:
A) The Requirements Management Plan, the Risk Management Plan, the Procurement Management Plan, the Change Management Plan, the Schedule Baseline, the Assumption Log, the Lessons Learned Register, the Milestone List, the Quality Reports, the Requirements Documentation, the Requirements Traceability Matrix, the Risk Register, and the Stakeholder Register.
B) The Project Agreements; the Change Requests, the Project Work Performance Data/Information/Reports; and the Procurement Documentation including the Statement ofWork, the Payment Information, the ContractorWork Performance Information, the Project Plans/Drawings, and the Correspondence Details.
C) Both Options above are Correct.
D) All Options above are Incorrect.
ANSWER: C