Question: Which scheduling technique determines project duration by analyzing activities with zero slack? A. Critical chain method B. Critical path method C. Sensitive analysis D. Resource
Which scheduling technique determines project duration by analyzing activities with zero slack?
A. Critical chain method B. Critical path method C. Sensitive analysis D. Resource smoothing