Question: The critical path in a project network is the A. Network path using the most resources. B. Network path with the most difficult activities. C.
The critical path in a project network is the A. Network path using the most resources.
B. Network path with the most difficult activities.
C. * Longest path through the network.
D. Shortest path through the network.