Question: The critical path in a project network is the Group of answer choices shortest path through the network. longest path through the network. network path
The critical path in a project network is the
Group of answer choices
shortest path through the network.
longest path through the network.
network path with the most difficult activities.
network path using the most resources.
network path with the most merge activities.