Question: 1 1 2 points Given is a PERT project network diagram as shown below. table [ [ Time , 0 , 1 . 5
points
Given is a PERT project network diagram as shown below.
tableTime
a The Project Completion time in decimal places
b The Earliest Start time, ES of Activity G type your answer... in decimal places
c The Latest Finish time, LF of Acitivity in decimal places
d The critical activities are ex type in critical activities as ABCD no comma, no space