Question: Given is a PERT project network diagram as shown below. Activity Start A B C D E F G H End Time 0 3.12 2.34
Given is a PERT project network diagram as shown below.
| Activity | Start | A | B | C | D | E | F | G | H | End |
| Time | 0 | 3.12 | 2.34 | 6.12 | 4.36 | 6.21 | 4.23 | 2.38 | 4.78 | 0 |
a) The Project Completion time = (in 2 decimal places)
b) The Earliest Start time, ES, of Activity G = (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C = (in 2 decimal places) d) The critical activities are = (ex. type in critical activities as ABCD, no comma, no space)