Question: QUESTION 2 Given is a PERT project network diagram as shown below. A T Start E E H End B D G Activity Time Start

QUESTION 2 Given is a PERT project network

QUESTION 2 Given is a PERT project network diagram as shown below. A "T Start E E H End B D G Activity Time Start 0 A 1.52 B 2.36 CTD 7.02 3.69 E|F|G|H 1.28 4.36 6.24 3.25 End 0 a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time. ES of Activity G= (in 2 decimal places) c) The Latest Finish time. LF, of Acitivity C = (in 2 decimal places) d) The critical activities are = (ex. type in critical activities as ABCD, no comma, no space)