Question: 1 2 - 6 Draw the network and identify the critical path. Also calculate the earliest - latest starting and finishing times for each activity:

12-6 Draw the network and identify the critical path. Also calculate the earliest-latest starting and finishing times for each activity:
\table[[Activity,Preceding Activity,Time (Weeks)],[A,-,4],[B,-,6],[C,A, B,7],[D,B,8],[E,B,5],[F,C,5],[G,D,7],[H,D, E,8],[I,F, G, H,4]]