Question: Considering the following project, determine the Critical Path. Activity Expected Duration Predecessor A 5 - B 3 A C 1 A, B D 5 C

Considering the following project, determine the Critical Path.

Activity

Expected Duration

Predecessor

A 5 -
B 3 A
C 1 A, B
D 5 C
E 10 B
F 2 E
G 3 D
H 4 F, G
I 5 H

Notes:

- Durations are in days.

a.

A, B, E, F, H, I

b.

A, B, H, I

c.

A, B, C, D, G, H, I

d.

A, B, E, F, I

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!