Question: Considering the following project, determine the Critical Path? Activity Expected Duration Predecessor A 5 - B 3 A C 1 A, B D 5 C

Considering the following project, determine the Critical Path?

Activity

Expected Duration

Predecessor

A 5 -
B 3 A
C 1 A, B
D 5 C
E 10 B
F 2 E
G 3 D
H 4 F, G
I 5 H

Notes:

- Durations are in days.

a.

A, B, H, I

b.

A, B, E, F, I

c.

A, B, E, F, H, I

d.

A, B, C, D, G, H, I