Question: 1. Develop the bar chart schedule of the project (1 Mark) 2. Draw the project baseline BCWS (3 Marks) 3. Draw the progress baselines ACWP

1. Develop the bar chart schedule of the project

1. Develop the bar chart schedule of the project (1 Mark) 2. Draw the project baseline BCWS (3 Marks) 3. Draw the progress baselines ACWP and BCWP up to day 7 (4 Marks) Explain in details how you get the numbers (2 marks) Activity Predecessors Duration Actual cost paid Cost $ per day actual percentage completed at day 7 300 100 400 100 A 2 600 B A 3 P- 3 400 33 1400 500 200 B B Po D 2 200 50 E D 3 100 0 0