Question: 1. Given the project information in the table below: TASK A FOLLOWS TASK(S) Start Start A,B B C,D DURATION (WEEKS) Normal Crash 3 2 2

1. Given the project information in the table

1. Given the project information in the table below: TASK A FOLLOWS TASK(S) Start Start A,B B C,D DURATION (WEEKS) Normal Crash 3 2 2 1 5 3 5 1 4 4 3 COST (DOLLARS) Normal Crash 500 600 400 450 600 550 640 400 550 750 E (a) Draw a PDM network diagram (b) Identify the critical path and duration (c) Calculate the slope of each activity (in terms of dollars/week) (d) Identify the task(s) you would crash and the incremental cost to reduce project duration by: i. One week ii. A second week iii. A third week iv. A fourth week