Question: 1 point In an earned value analysis, the BCWS on a project is 50, the BCWP is 60 and the ACWP is 80. Which of

1 point

In an earned value analysis, the BCWS on a project is 50, the BCWP is 60 and the ACWP is 80. Which of the following is true? (More than one choice may be correct)

1.SPI is 1.2

2.CPI is 1.25

3.SPI is 1.6

4.CPI is 0.75

This is a project management question.