Question: Setup Cost = $771 per setup Holding cost = $0 per unit per week Lead Time = 1 Week Safety Lead Time = 1 Week

Setup Cost = $771 per setup

Holding cost = $0 per unit per week

Lead Time = 1 Week

Safety Lead Time = 1 Week

Scrap Allowance = 5.9%

Lot Size = LFL (Lot-for-Lot)

Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirements 461 513 569 501 617 667 583 699 600 689 530 631 Scheduled Receipts 470 Beg. Inventory 818 Net Requirements Ending Inventory Planned Order Receipts Planned Order Releases What are your Planned Order Releases for Week 5?

Round up to a whole unit!