Question: 13500 Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B 2. 1 2400 2800 3

13500
13500 Consider the following: Activity Normal
Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B 2. 1 2400 2800 3 3 500 500 8 4 2200 2600 A 6 3 600 1200 B F 3 3600 4200 G 4 2000 2000 D.E What is the total cost of completing this project with the normal completion time. - 6 NN WW Note: Do not include any unit of measure. Your