Question: please help me in this Question 6 (1 point) Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor 4 3 2200
please help me in this
Question 6 (1 point) Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor 4 3 2200 2600 B 2 1 2400 2800 C 3 3 500 500 D 8 4 2200 2600 A E 6 3 600 1200 B F 3 2 3600 4200 C 4 G 2 1700 2000 DE What is the total cost of completing this project with the normal completion time. IU WU NO Note: Do not include any unit of measure. Your
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
