Question: Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 2 1 2400 2800 3 3 500

Consider the following: Activity Normal time
Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 2 1 2400 2800 3 3 500 500 D 8 4 2200 2600 A 6 3 600 1200 B F 3 2. 3600 4200 C G 4 2 1600 2000 DE What is the total costlof completing this project with the normal completion time. Note: Do not include any unit of measure.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!