Question: please help me in this Question 6 (1 point) Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3
please help me in this
Question 6 (1 point) Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 2 1 2400 2800 C 3 3 500 500 D 8 4 2200 2600 A 6 3 600 1200 B 3 2 3600 4200 G 4 2 1700 2000 DE What is the total cost of completing this project with the normal completion time. Note: Do not include any unit of measure.