Question: 16.3. Consider a project with the following activity list. Activity Immediate Predecessors Estimated Durantion (months) A - 1 B A 2 C B 4 D
16.3. Consider a project with the following activity list.
Activity Immediate Predecessors Estimated Durantion (months)
A - 1
B A 2
C B 4
D B 3
E B 2
F C 3
G D,E 5
H F 1
I G,H 4
J I 2
K I 3
L J 3
M K 5
N L 4
a. Construct the project network for this project.
b. Find the earliest start time and earliest finish time for each activity.
c. Find the latest start time and latest finish time for each activity.
d. Find the slack for each activity. Which of the paths is a critical path?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
