Question: If an activity whose normal duration is 5 8 days can be shortened to 3 2 days for an added cost of $ 8 5

If an activity whose normal duration is 58 days can be shortened to 32 days for an added cost of $8520, what is thecrash cost per period? (please round off to twodecimal digits)