Question: #2 - Build the Flow and Confirm Critical Path Task Duration Task ID Task Description Task Predecessors (hours) A Project start B Buy materials for
#2 - Build the Flow and Confirm Critical Path

Task Duration Task ID Task Description Task Predecessors (hours) A Project start B Buy materials for A A 10 C Buy materials for B A 20 Build A B, C 30 E Build B B. C 20 Polish and finish B E 40 G Join A and B D. F 20 H Project finish G C